How Many Man-Hours Are Needed to Assemble a CAT 793D Dump Box
#1
Assembling a Caterpillar 793D dump box typically requires between 250 to 400 man-hours depending on crew size, equipment availability, and environmental conditions. With a skilled team and proper lifting gear, a single box can be completed in under a week.
Caterpillar 793D background and dump box configuration
The Caterpillar 793D is a high-capacity off-highway mining truck introduced in the early 2000s. It features:
  • A payload capacity of 240 tons
  • A gross machine weight exceeding 386 tons
  • A 2,433 hp diesel-electric powertrain
  • Modular dump box design for field assembly
Caterpillar, founded in 1925, has dominated the mining truck market with its 793 series, which includes the 793A through 793F. The 793D was widely deployed in copper, coal, and iron ore mines across North America, South America, and Australia. Its dump box is shipped in sections and assembled on-site to reduce transport costs and accommodate regional customization.
Dump box assembly process and labor breakdown
The dump box ensemble involves:
  • Positioning the base frame using overhead cranes or large forklifts
  • Aligning and welding side panels and front bulkhead
  • Installing the canopy and rear spill guard
  • Reinforcing structural seams with multi-pass welds
  • Mounting hydraulic lift points and wear liners
Typical labor breakdown:
  • Structural welding: 120–180 hours
  • Panel alignment and bolting: 40–60 hours
  • Hydraulic and liner installation: 30–50 hours
  • Inspection and touch-up: 20–30 hours
A crew of 4–6 certified welders and fitters can complete the job in 4–6 days under ideal conditions. Weather, crane availability, and site layout can extend this timeline.
Factors affecting man-hour estimates
  • Crew experience: Skilled teams reduce rework and alignment time
  • Equipment access: Overhead cranes and mobile lifts accelerate positioning
  • Welding method: MIG welding is faster than stick welding but requires clean surfaces
  • Pre-fabrication quality: Factory-cut panels with precise tolerances reduce fitting time
  • Environmental conditions: Cold weather slows welding and increases prep time
One contractor in Fort McMurray noted that assembling 15 dump boxes for a fleet expansion required staggered scheduling and multiple crane teams. Each box took approximately 320 man-hours, with additional time for quality assurance and paint touch-up.
Recommendations for project planning
  • Request factory assembly guides from Caterpillar or authorized dealers
  • Use laser alignment tools for panel positioning
  • Schedule crane time in advance to avoid delays
  • Assign a dedicated QA inspector to monitor weld integrity
  • Document man-hours per box to refine future bids
If bidding on multiple units, consider economies of scale—shared tooling, repeatable workflows, and experienced crews can reduce per-unit labor.
Conclusion
Assembling a CAT 793D dump box is a labor-intensive but well-defined process. With proper planning, skilled labor, and adequate lifting equipment, each box can be completed in 250–400 man-hours. For large orders, staggered scheduling and standardized workflows are key to maintaining efficiency and quality.
Reply


Possibly Related Threads…
Thread Author Replies Views Last Post
  McLaren Tracks Failing After 300 Hours: Common Causes and Solutions MikePhua 0 3 36 minutes ago
Last Post: MikePhua
  Diagnosing Slow Bucket Dump on Komatsu PC250LC-6LE MikePhua 0 3 6 hours ago
Last Post: MikePhua
  Ford 555B Dump Valve Removal: A Step-by-Step Guide MikePhua 0 3 7 hours ago
Last Post: MikePhua
  Why Did the Hydraulic Motor Fail on a Bobcat FRC200XT After Just 50 Hours MikePhua 0 7 10-18-2025, 08:13 PM
Last Post: MikePhua
  Diagnosing Air Dump Valve Issues on a Modified 1988 Western Star Dump Truck MikePhua 0 13 10-18-2025, 05:43 PM
Last Post: MikePhua
  Diagnosing EUP Failure and Misfire in a Mack AI-475 Dump Truck MikePhua 0 24 10-14-2025, 02:17 PM
Last Post: MikePhua
  Tailgate Release Systems in Dump Trucks Mechanical Logic and Field Solutions MikePhua 0 46 10-05-2025, 06:40 PM
Last Post: MikePhua
  Restoring a 1993 Ford LN8000 Dump Truck and Sourcing Obsolete Parts MikePhua 0 50 09-28-2025, 08:54 PM
Last Post: MikePhua
  Troubleshooting the 2017 Kenworth T880 Dump Truck Code 1321 FMI 14 MikePhua 0 34 09-28-2025, 02:20 PM
Last Post: MikePhua
  Working Hours Correction in Heavy Equipment: A Practical Guide MikePhua 0 40 09-27-2025, 07:58 PM
Last Post: MikePhua
  Volvo A25C No Dump or Steering Issues MikePhua 0 47 09-27-2025, 07:22 PM
Last Post: MikePhua
  Lift and Dump Failure in the Bobcat 873G and Hydraulic Control Diagnostics MikePhua 0 38 09-25-2025, 07:41 PM
Last Post: MikePhua
  Maintaining and Replacing Tailgate Air Cylinders on Ox Bodies Dump Beds MikePhua 0 41 09-25-2025, 11:30 AM
Last Post: MikePhua
  Troubleshooting and Maintaining a 1990 Freightliner 4700 Dump Truck MikePhua 0 45 09-25-2025, 10:58 AM
Last Post: MikePhua
  Material Sticking in Dump Box: Solutions and Tips MikePhua 0 47 09-25-2025, 01:06 AM
Last Post: MikePhua

Forum Jump:


Users browsing this thread: 1 Guest(s)