Accurate bidding for small excavation jobs requires a clear understanding of scope, realistic cost breakdowns, and contingency planning. Whether you're digging footings, clearing a pad, or trenching utilities, a well-structured estimate protects your margins and builds client trust.
Project Scope and Site Variables
Before pricing any excavation job, define the scope in detail. This includes:
Terminology and Cost Components
A contractor in Idaho bid a small trenching job at $1,800, assuming sandy soil. Upon arrival, he hit compacted glacial till and spent two extra days hammering through it. His profit vanished. Since then, he adds a soil clause to every bid and includes a contingency line item.
Another operator in Georgia priced a pad excavation at $2,400 but forgot to include dump fees. After hauling 18 tons to a landfill, he lost $400. He now uses a checklist for every bid, including disposal, erosion control, and access notes.
Bid Presentation and Client Communication
Small excavation bids may seem straightforward, but hidden variables can erode profit quickly. By defining scope, calculating realistic costs, and communicating clearly with clients, contractors can bid confidently and deliver quality work. A disciplined approach to estimating not only protects margins—it builds a reputation for reliability and professionalism.
Project Scope and Site Variables
Before pricing any excavation job, define the scope in detail. This includes:
- Total area and depth of excavation
- Soil type and compaction level
- Access limitations and haul routes
- Presence of utilities or obstructions
- Required finish grade or compaction specs
Terminology and Cost Components
- Mobilization: The cost to transport equipment to and from the site.
- Production Rate: The volume of material moved per hour, affected by machine size, operator skill, and soil conditions.
- Spoil Management: Whether material is stockpiled, spread, or hauled offsite.
- Overdig: Extra excavation beyond plan dimensions to allow for formwork or compaction.
- Contingency: A buffer for unexpected issues, typically 10–15% of total cost.
- Equipment (e.g., skid steer, mini excavator): $75–$150/hour
- Operator labor: $35–$60/hour
- Fuel and wear: $10–$20/hour
- Dump fees (if hauling): $15–$50/ton depending on region
- Mobilization: $150–$500 depending on distance
- Markup: 10–25% depending on competition and risk
- 8 hours equipment: $1,000
- 8 hours labor: $480
- Fuel and wear: $120
- Dump fees: $300
- Mobilization: $250
- Contingency: $215
- Total before markup: $2,365
- Final bid with 15% markup: $2,720
A contractor in Idaho bid a small trenching job at $1,800, assuming sandy soil. Upon arrival, he hit compacted glacial till and spent two extra days hammering through it. His profit vanished. Since then, he adds a soil clause to every bid and includes a contingency line item.
Another operator in Georgia priced a pad excavation at $2,400 but forgot to include dump fees. After hauling 18 tons to a landfill, he lost $400. He now uses a checklist for every bid, including disposal, erosion control, and access notes.
Bid Presentation and Client Communication
- Break down the estimate into clear categories: excavation, hauling, mobilization, etc.
- State assumptions (e.g., soil type, access, weather conditions).
- Include exclusions (e.g., utility locating, rock removal, permits).
- Offer optional add-ons like compaction or gravel base.
- Use plain language to build trust and avoid confusion.
Small excavation bids may seem straightforward, but hidden variables can erode profit quickly. By defining scope, calculating realistic costs, and communicating clearly with clients, contractors can bid confidently and deliver quality work. A disciplined approach to estimating not only protects margins—it builds a reputation for reliability and professionalism.